Typical Timing Overview - Approximately 8 Months

Truck lead time from the Factory is typically around 18-20 weeks with the SPED required
Approximately 4 weeks required for the Automation Preparation.
FAT Preparation 3 weeks.
Mapping of Customer application and Safety testing 1 week.
Functional Testing 1 week.
Ramp up 2 weeks.
Hypercare 3 Months.